Monday, March 7, 2016

Koppers Site

For those keeping up with what is going on at the old Koppers wood treating site, there apparrently has been little movement on the Bright Fields project. Here is the latest report on the cleanup:

Status Report – February 2016 Former Koppers Wood-Treating Site Carbondale, Illinois Page: 2/2 Items Performed/Completed Since Previous Report:
• During the week of February 1, 2016, FTS conducted the first 2016 semiannual RCRA groundwater monitoring event (reflecting the recently revised/approved GMP). •

On February 12, 2016, Arcadis submitted to USEPA a Groundwater Monitoring Network Modifications Report, which summarized groundwater monitoring network modifications completed at the Site, and presented the analytical results for soil samples collected during drilling for certain of the new monitoring wells along the southern property boundary of the Site. USEPA issued a letter approving the report on February 18, 2016. •

 On February 26, 2016, FTS submitted to USEPA the 2015 Annual RCRA Groundwater Monitoring Report. • Beazer, USEPA and others participated in a corrective action coordination conference call on February 18, 2016.
• Beazer continued post-construction OMM activities (e.g., DNAPL thickness measurements/removal, CAMU leachate monitoring/removal, Site inspections, etc.). DNAPL removal volumes are summarized as follows: RW-23 South Trench Sump North Trench Sump February 2016 Total (gal): 48 99 0 Cumulative Total (gal): 8,046 19,503 655

 Items Anticipated to be Performed/Completed over the Next One to Two Months:
• Beazer, USEPA and others will continue to participate in corrective action coordination conference calls, including specific calls to discuss the ecological risk-based remedy, the sediment MNR scope of work/fish consumption advisory, and institutional controls.
• Beazer will propose an approach for evaluating trends in visual observations that could be used to assess the proposed probing/reconnaissance portion of the MNR program.

Items Anticipated to be Performed/Completed over the Next Two to Six Months
: • Beazer will continue to advance proposed future Site uses, including conservation land use and commercial solar energy.
• USEPA will conduct a public meeting in Carbondale. Items that May Cause Delay in Implementing Future Activities 

Tuesday, May 19, 2015

Koppers Report

Here's the report on the cleanup at the Koppers site for April:

Status Report – April 2015
Former Koppers Wood-Treating Site
Carbondale, Illinois
Items Performed/Completed Since Previous Report:
 On April 27, 2015, Beazer submitted to USEPA a draft revision of the Human Health Risk Assessment
(HHRA), addressing USEPA’s March 5, 2015 comments.
 On April 28, 2015, ARCADIS (on behalf of Beazer) submitted a letter to USEPA responding to an April
23, 2015 email regarding the potential effects of solar farms on ecological habitat.
 Beazer, USEPA and others participated in corrective action coordination conference calls on April 9 and
23, 2015.
 On April 23, 2015, Beazer, USEPA, and others participated in a conference call to discuss an ecological
risk management approach for the Site.
 Beazer continued post-construction OMM activities (e.g., DNAPL thickness measurements/removal,
CAMU leachate monitoring/removal, Site inspections, etc.). DNAPL removal volumes are
summarized as follows:
RW-23 South Trench Sump North Trench Sump
April 2015 Total (gal): 35 44 26
Cumulative Total (gal): 7,708 18,710 551
Items Anticipated to be Performed/Completed over the Next One to Two Months:
 Beazer will propose a draft scope of a monitored natural recovery (MNR) program for residual impacted
sediment areas.
 Beazer will submit to USEPA a table and figures presenting a summary of various ecological-risk-based
remediation scenarios.
 Beazer will submit additional information requested by USEPA regarding the applicability of potential
ecological risk evaluations to shrews on a Site-wide versus area-specific basis.
 USEPA will provide comments on the October 2008 Draft Groundwater Monitoring Plan and all other
relevant information submitted over the past several months concerning this item.
 USEPA will review the April 27, 2015 draft revised HHRA to confirm the revision addresses USEPA
comments. The HHRA will be finalized pending USEPA’s acknowledgement that their March 5, 2015
comments have been satisfactorily addressed.
 Beazer and USEPA will continue coordinating regarding potential ecological risk with the goal of
identifying an acceptable basis for identifying any remaining areas subject to remediation to address
potential ecological risk.
 Beazer, USEPA and others will continue to participate in corrective action coordination conference calls.
0811512248_C'dale Apr 2015 StatusRpt_051915.doc 2
Status Report – April 2015
Former Koppers Wood-Treating Site
Carbondale, Illinois
Items Anticipated to be Performed/Completed over the Next Two to Six Months:
 Beazer will continue to advance proposed future Site uses, including conservation land use and
commercial solar energy.
 USEPA will conduct a public meeting in Carbondale.
Items that May Cause Delay in Implementing Future Activities and Efforts (if any) to Limit Such
Delays:
 None.

Monday, April 27, 2015

Koppers

For those following the Kopper's site cleanup, here is the latest update on how it is progressing:

Items Performed/Completed Since Previous Report:
 On March 5, 2015, USEPA provided written comments on the Human Health Risk Assessment (HHRA)
that was submitted by Beazer on November 26, 2014.
 On March 24, 2015, the Carbondale City Council approved a Special Use Permit for a commercial solar
energy facility at the Site.
 Beazer, USEPA and others participated in corrective action coordination conference calls on March 12
and 26, 2015.
 USEPA and ARCADIS participated on a conference call on March 19 to discuss USEPA comments
related to developing a revised groundwater monitoring program for the Site.
 Beazer continued post-construction OMM activities (e.g., DNAPL thickness measurements/removal,
CAMU leachate monitoring/removal, Site inspections, etc.).
 Beazer collected approximately 87 gallons of DNAPL from the barrier trench and approximately 46
gallons of DNAPL from recovery well RW-23 during this reporting period. The approximate total
DNAPL volumes collected through March 2015 are 19,190 gallons from the barrier trench and 7,673
gallons from RW-23.
Items Anticipated to be Performed/Completed over the Next One to Two Months:
 Beazer, USEPA and others will work on action items from the February 18, 2015 meeting, as
documented in a February 23, 2015 letter from Beazer and as discussed during the March 12, 2015
conference call.
 Beazer will submit a revised HHRA to USEPA.
 USEPA will provide comments on the October 2008 Draft Groundwater Monitoring Plan.
 Beazer and USEPA will participate in a conference call to discuss an ecological risk management
approach for the Site.
 Beazer will propose a draft scope of a monitored natural recovery (MNR) program for residual impacted
sediment areas.
 Beazer, USEPA and others will continue to participate in corrective action coordination conference calls.
Items Anticipated to be Performed/Completed over the Next Two to Six Months:
 Beazer will continue to advance proposed future Site uses, including conservation land use and
commercial solar energy.
 USEPA will conduct a public meeting in Carbondale.
Items that May Cause Delay in Implementing Future Activities and Efforts (if any) to Limit Such
Delays:
 None.

Monday, October 13, 2014

Koppers Update

Here's an update from Beazer on the company's activity cleaning up the former Kopper's site:

On September 5, 2014, USEPA provided preliminary comments on Attachments 1 and 2 of the Human Health Risk Assessment Work Plan (HHRA Work Plan).

 On September 11, 2014, Beazer submitted a letter to USEPA responding to USEPA’s August 19 and September 5, 2014 comments on the HHRA Work Plan.

 On September 19, 2014, USEPA submitted a follow-up letter to Dr. Brian Klubek (Concerned
Carbondale Citizens), providing a modified response regarding groundwater sampling for dioxins/furans.

 On September 26, 2014, USEPA approved Beazer’s September 11, 2014 responses to USEPA’s
comments on the HHRA Work Plan, and requested a revised/final HHRA Work Plan by October 17,
2014.

 Beazer, USEPA and others participated in corrective action coordination conference calls on September 4 and 18, 2014.

 Beazer continued post-construction OMM activities (e.g., DNAPL thickness measurements/removal, CAMU leachate monitoring/removal, Site inspections, etc.).

 Beazer collected approximately 86 gallons of DNAPL from the barrier trench and approximately 28 gallons of DNAPL from recovery well RW-23 during this reporting period. The approximate total
DNAPL volumes collected through September 2014 are 18,530 gallons from the barrier trench and
7,504 gallons from RW-23.

Monday, September 15, 2014

Koppers Report

Here's what Beazer, the company tasked with cleaning up the old Koppers site (where Brightfields hopes to locate its solar production array), has accomplished since the last report:

Items Performed/Completed Since Previous Report:
 On August 4, 2014, Beazer submitted a letter to USEPA addressing USEPA’s suggestion of
groundwater sampling for dioxins/furans as stated in the agency’s July 29, 2014 letter responding to
questions received from the Concerned Carbondale Citizens.

 On August 20, 2014, USEPA provided Beazer with preliminary comments on the July 28, 2014 Human Health Risk Assessment Work Plan.

 Beazer, USEPA and others participated in corrective action coordination conference calls on August 7 and 21, 2014.

 Beazer continued post-construction OMM activities (e.g., DNAPL thickness measurements/removal, CAMU leachate monitoring/removal, Site inspections, etc.).

 Beazer collected approximately 123 gallons of DNAPL from the barrier trench and approximately 38 gallons of DNAPL from recovery well RW-23 during this reporting period. The approximate total
DNAPL volumes collected through August 2014 are 18,444 gallons from the barrier trench and 7,476
gallons from RW-23.

Thursday, February 13, 2014

Concerned Citizens of Carbondale Letter

The city has posted a copy of the  letter of questions it has received from the Concerned Citizens of Carbondale group, along with the city's response to said questions.. I found the first question asked to set the tone for the following 8 questions:

What is/are the reason(s) that the Carbondale City Council is not allowing the toxic waste site to
be cleansed as thoroughly as possible, in accordance with EPA standards/regulations: an
estimated eight years of continuous sterilization work facilitated through aggressive
maintenance?


Needless to say, the city has not impeded the clean up of the Koppers site.  One of the major reasons it has taken so long is that the EPA continually changes the requirements it has set to certify the site as clean.  I have listened to and read several of the reports from Beazer which indicate the EPA has oversight of cleaning the site.  The city has no input or affect on how quickly or slowly the cleanup process moves.